Four situations, four phased strategies

Can you close?Lease windowBudgetStructure stateStrategy
No, daily tradingMonths to runLeanSound steel portalOvernight bay swaps onto the retained frame
One closed day a weekMonths to runMidMixed baysClosed-day swaps, worst bay first, always keep one entrance open
Yes, between tenantsRent-free voidFullFailing frameFull strip inside the void, new modular front
Seasonal dips onlyMulti-year leasePhased spendSoundSplit phases by budget year, reuse modular bays later

RELATED READING
The budget column is the one most often misread. A low headline price that assumes a full close-down can cost more in lost trade than the premium phased facade works carry. The warning signs are set out in our facade quotation red flags guide.

Survey while the till is open

Phased facade works begin with a one-week survey that does not close the shop. Laser scanning records the existing steel portal and each bay’s substrate while trading continues inside.

laser surveyor scanning the existing steel portal frame of a 1970s shopfront, red dots on weathered steel

On the Bloom & Co. record in Melbourne, the survey found the original steel portal behind the 1970s smoked glass was sound. Reusing it saved two weeks and enough budget to fund the new oversized pivot entry. The survey also produces the as-built drawings that the permit authority needs, which on a small project is often the same drawing package the factory uses. Because the measurements are taken with the shop open, the survey must be scheduled around peak hours so the equipment does not block the entrance or the queue.

The overnight bay swap, hour by hour

In phased facade works, the overnight bay swap is a small production with a strict curtain. The sequence runs: close the shop, erect hoarding and pedestrian protection, remove the old bay, fit the new unit, seal the joints, clean the pavement, remove the barriers and open on time. On the Bloom & Co. shopfront record from Melbourne, a 120 m² renovation run as phased facade works while the lease kept trading, the till never closed for more than one consecutive day because the programme built every swap around the trading calendar. Noise windows are agreed with the landlord and the local council; the National Access and Scaffolding Confederation publishes practical guidance on safe hoarding and pedestrian routes at nasc.org.uk. The morning checklist is as important as the night shift: glass smears, dust on the threshold, loose tape and a forgotten traffic cone can undo a clean install before the first customer arrives.

Keep the frame, change the face

Phased facade works should usually retain the existing structure. Demolition is justified only when the survey shows the frame cannot carry the new loads, the substrate is rotten or the lease void is long enough to absorb the delay.

modular shopfront bay in production inside a facade workshop, tooling marks and clamps

Retaining the frame turns the project into a component swap: new aluminium framing, new glass and new seals bolted onto the old portal. That is exactly how the Corner Grocer in Phuket was rebuilt. Starveil Facade’s engineering desk produced three storefront options priced in a single proposal, every component sized so the local builder’s small crew could carry it by hand down a narrow lane, and the full envelope went up in nine working days. See the Corner Grocer project record for the component sizing and permit-drawing timeline. The same component logic pays off years later, and our guide to ordering replacement panels years later shows which handover records make a single-bay swap straightforward.

The lease window and the second order

In phased facade works the lease is a design document. Before pricing, read the clauses that govern external alterations, noise hours, hoarding, liability for footpath obstruction and access to shared services. Agree the allowed night hours, the permitted decibel limit, the maximum hoarding height and who pays for any damage to the pavement. Modular systems make the second phase cheaper because the factory jigs, glass schedules and bracket patterns already exist. The Bloom record saw the client order two matching bays within six months, and the repeat order skipped the survey and design phase that the first phase had funded. A multi-year lease therefore justifies a slightly higher first-phase specification because the same module can be reused or extended later.

Send photographs, dimensions and the trading calendar

Send the Starveil Facade team clear photographs of the existing shopfront from street level, rough width and height dimensions, and a calendar marking the days the business can and cannot close. Include the lease clause on external alterations if you have it. The return package will contain a route recommendation from the phasing matrix, a bay-by-bay sequence of phased facade works aligned to your trading hours, and a fixed-scope proposal. No architect is required to start.

What to remember

  • Survey the existing frame before designing the new one; what you keep is the budget you free up.
  • In phased facade works the overnight swap is a production with a morning deadline, not just an installation.
  • Hoarding can advertise the renovation if it carries a readable brand message and a clean edge.
  • Read the lease before pricing; the allowed noise hours and hoarding rules decide the programme.
  • Modular systems make the second order faster and cheaper because the engineering is already paid for.
  • A factory audit of the Foshan engineering and fabrication plant, covered in our curtain wall factory audit guide, confirms the build quality before the bays ship.

RELATED READING

For more guidance on phased facade upgrades, explore our facade renovation hub. Learn about replacement facade panels for future bay upgrades, and use our curtain wall factory audit guide to assess manufacturing quality before production.

Frequently asked questions

Can a shop stay open during phased facade works?

Yes, when phased facade works move bay by bay. The programme keeps the shop trading by separating survey, factory fabrication and overnight installation so only one bay is interrupted at a time.

How long does each overnight bay swap take?

Most single bay swaps are completed in one night, with the shop ready to open the next morning. The critical path is not the fitting; it is the morning cleanup, sealant cure and barrier removal that protects the first customer.

Should we keep the existing frame or demolish it?

Keep it if the survey shows the steel or concrete portal is sound. Demolition is only justified when the substrate is failing, the new loads exceed the old capacity, or the lease gives a long enough void to absorb a full rebuild.

What lease clauses matter for a trading renovation?

The key clauses cover permitted external alterations, allowed work hours, noise limits, hoarding height, footpath liability and access to shared services. Retail Design Institute best-practice notes on store planning are available at retaildesigninstitute.org.

How much trade do we lose during phased facade works compared with a full closure?

Phased works disturb one bay at a time, so the loss is measured in disrupted mornings rather than closed weeks. The phasing matrix trades a small installation premium against the takings a full closure would forfeit, and on the published Bloom & Co. reference study, a 120 m² Melbourne shopfront rebuilt while the lease kept trading, the till never closed for more than one consecutive day.

Can a second phase reuse what the first phase paid for?

Yes, when the first phase is specified modularly. The factory jigs, glass schedules and bracket patterns already exist, so matching bays skip the survey and design cost. The Bloom record shows two matching bays ordered within six months on exactly that basis.

About the author

Blake

Blake

I turn curtain wall and facade designs into buildable, code-compliant systems — from structural calculations and shop drawings to fabrication-ready details, all designed, calculated and coordinated in-house.

Why trust me:

15+ years in curtain wall facade engineering; 1.2M+ m² of facade area engineered
Core expertise: stick-built & unitized systems, structural glazing, wind load, thermal and solar performance calculations
Works to EN 13830, ASTM/AAMA and AS 2047
Specializes in GCC and North American climate performance — 50°C Riyadh heat, Dubai coastal salt, US freeze-thaw